One of the first questions Arizona homeowners ask when planning a pool is simple: how long is this going to take? The answer depends on several factors, including the time of year, permit processing times, design complexity, and whether unexpected challenges like caliche rock or drainage issues arise.
Here's a realistic breakdown of the pool construction timeline in Arizona.
Phase 1: Design and Pre-Construction (2–6 Weeks)
Before a single shovel hits the ground, there's significant planning work to complete:
Permit approval times vary by municipality. In cities like Gilbert and Queen Creek, the process can take 3–5 weeks. In Scottsdale and Paradise Valley, plan for 4–6 weeks. Carefree and Fountain Hills may have different timelines depending on current workload.
Phase 2: Excavation (1–3 Days)
Once permits are approved, excavation typically takes one to three days depending on pool size and soil conditions. Arizona's notorious caliche layer can slow this phase if it's deep or thick. Experienced builders plan for this and bring the right equipment.
Phase 3: Steel and Plumbing (3–5 Days)
After excavation, the steel rebar framework is installed, followed by plumbing rough-in. This phase requires an inspection before moving forward, which can add one to three business days depending on the city's inspection schedule.
Phase 4: Shotcrete or Gunite Shell (1–2 Days)
The pool shell — either shotcrete or gunite — is applied in one or two days. Then it must cure properly, which takes 28 days minimum. During this time, the shell is kept wet daily to prevent cracking in Arizona's dry heat.
Phase 5: Tile, Coping, and Deck (1–2 Weeks)
This phase includes all tile work, coping installation around the pool edge, and the surrounding deck. Decking material choices — travertine, cool deck, concrete — affect timing slightly. Equipment installation and electrical work are completed during this phase as well.
Phase 6: Plaster or Pool Finish (1–2 Days + Startup)
The final interior finish (plaster, pebble, or quartz) is applied, then the pool is immediately filled with water. Startup and water chemistry balancing takes another 7–10 days before the pool is safe to swim in.
Total Timeline: 8–14 Weeks
From permit submission to first swim, most Arizona pools take 8 to 14 weeks. Simple designs in cities with faster permit processing can fall closer to 8 weeks. Complex custom pools in communities like Paradise Valley or Arcadia Proper with more involved permitting may take 14 weeks or longer.
The most common cause of delays? Starting too late in the season. Homeowners who want a pool by Memorial Day should begin conversations with their builder no later than January.
Start Your Pool Project Today Island Style Pools manages every phase of construction from design to startup throughout the Valley and Tucson area. Contact us today to get your project on the schedule.
You get:
Office location
2364 S Airport Blvd #2, Chandler, Arizona, 85286Send us an email
[email protected]